London

DP World Crane Rails

2024

The Challenge

This project posed specific challenges that demanded a high-performance solution.

The Challenge:

We needed to grout large areas under the crane rail base plates – the total a whopping 860m x 460mm!
This required a great deal of Premcrete’s Epodure HS Epoxy Grout – in total, 1,358 x 26kg units!
We needed to ensure the grout flows seamlessly through narrow gaps while maintaining high strength.

The Solution:

To meet the requirements of grouting large base plates, Premcrete provided the Epodure HS Epoxy Resin Grout.
This high-strength grout, developed in collaboration with Bemo Rail BV, ensured seamless flow through narrow gaps and exceptional mechanical properties, making it suitable for the demanding pressures of crane rail installations.

Key Advantages:

Compliance: met stringent project requirements effortlessly
Training and support: conducted site trials and trained staff via the Premcrete Academy
Customer service: ensured reliable stock availability and seamless support.

Test

Products Used

Project Details

Project Location:
London
Main Contractor:
Architect:
Structural Engineer:
Groundworks Contractor:
Systems Installed
Type A:
Type B:
Type C:
Levels below ground:
Share this Case Study

Related Case Studies

Devon
Parsons Tunnel
Morgan Sindall
London
Colne Valley Viaduct
Align JV
Devon
Parsons Tunnel
Morgan Sindall
London
Colne Valley Viaduct
Align JV